TY - GEN
T1 - Web-Based 4D Visual Production Models for Decentralized Work Tracking and Information Communication on Construction Sites
AU - Lin, Jacob J.
AU - Golparvar-Fard, Mani
N1 - Publisher Copyright:
© ASCE.
PY - 2016
Y1 - 2016
N2 - Tracking work-in-progress on construction sites requires establishing two-way flow of information between project managers and field personnel so that changes and performance issues with respect to task assignments, scope, status, and completion can be communicated effectively. Recent research has focused on minimizing decision bottlenecks and lowering coordination costs caused by inefficiencies in information sharing between project participants via leveraging 4D BIM and mobile computing platforms. Nevertheless, effective communication of who is doing what work in what location and comparing actual and planned progress in a timely fashion still requires preparing/updating 4D BIM with details that can reflect daily tasks, breaking the model into various locations, and then capturing task information onsite and manually updating them to 4D BIM. To address these inefficiencies, this paper presents a web-based work tracking system that builds on 4D visual production models, generated via superimposing image-based 3D point clouds with 4D BIM. These models allow project participants to directly commit to work tasks without the need for addressing difference in the level of detail between 4D BIM and actual work in progress, communicate performance deviations based on commitments from coordination sessions, measure readiness of the upcoming tasks based on inter-dependencies of current schedule tasks and their constraints, and highlight locations that are at-risk of potential performance problems. The benefits of the system in providing enhance awareness of ongoing work and better flow of information are discussed based on experiments conducted on a large-scale construction project.
AB - Tracking work-in-progress on construction sites requires establishing two-way flow of information between project managers and field personnel so that changes and performance issues with respect to task assignments, scope, status, and completion can be communicated effectively. Recent research has focused on minimizing decision bottlenecks and lowering coordination costs caused by inefficiencies in information sharing between project participants via leveraging 4D BIM and mobile computing platforms. Nevertheless, effective communication of who is doing what work in what location and comparing actual and planned progress in a timely fashion still requires preparing/updating 4D BIM with details that can reflect daily tasks, breaking the model into various locations, and then capturing task information onsite and manually updating them to 4D BIM. To address these inefficiencies, this paper presents a web-based work tracking system that builds on 4D visual production models, generated via superimposing image-based 3D point clouds with 4D BIM. These models allow project participants to directly commit to work tasks without the need for addressing difference in the level of detail between 4D BIM and actual work in progress, communicate performance deviations based on commitments from coordination sessions, measure readiness of the upcoming tasks based on inter-dependencies of current schedule tasks and their constraints, and highlight locations that are at-risk of potential performance problems. The benefits of the system in providing enhance awareness of ongoing work and better flow of information are discussed based on experiments conducted on a large-scale construction project.
UR - http://www.scopus.com/inward/record.url?scp=84976406270&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=84976406270&partnerID=8YFLogxK
U2 - 10.1061/9780784479827.173
DO - 10.1061/9780784479827.173
M3 - Conference contribution
AN - SCOPUS:84976406270
T3 - Construction Research Congress 2016: Old and New Construction Technologies Converge in Historic San Juan - Proceedings of the 2016 Construction Research Congress, CRC 2016
SP - 1731
EP - 1741
BT - Construction Research Congress 2016
A2 - Perdomo-Rivera, Jose L.
A2 - Lopez del Puerto, Carla
A2 - Gonzalez-Quevedo, Antonio
A2 - Maldonado-Fortunet, Francisco
A2 - Molina-Bas, Omar I.
PB - American Society of Civil Engineers
T2 - Construction Research Congress 2016: Old and New Construction Technologies Converge in Historic San Juan, CRC 2016
Y2 - 31 May 2016 through 2 June 2016
ER -