TY - GEN
T1 - Estimating the actual cost of transmission system congestion
AU - Overbye, T. J.
N1 - Funding Information:
The author would like to acknowledge the support of TVA, the U.S. Department of Energy through the Consortium for Electric Reliability Technology Solutions (CERTS) program, PSERC (Power System Engineering Research Center), and PowerWorld Corporation.
Publisher Copyright:
© 2003 IEEE.
PY - 2003
Y1 - 2003
N2 - This paper describes a methodology that could be used by a utility to estimate the actual cost of congestion on its transmission system using limited, non-state estimator data. The assumed problem inputs are a power flow model of an entire interconnected grid (i.e., the eastern interconnect), costs for the utility's generators, and then hourly values of the utility's generation, load and tie-line flows over the study time period. Due to the common lack by most utilities of external measurements, the system is first equivalenced to retain only the utility's own internal buses and a small subset of the external buses. Then, for each hour, the utility's load and generation is set to match their historical values, while the external generation is adjusted to match the tie-line flows. Next, an economic dispatch is performed to determine the unconstrained cost. Finally, a security constrained OPF (SCOPF) is solved to take into account base case and contingent constraints. The methodology uses a complete ac power flow formulation to accurately estimate the impact of voltage constraints and the incremental impact of system losses. The inclusion of hydro generation is also considered. For illustrative purposes only, the methodology demonstrated on the TVA system using publicly available data transmission system data.
AB - This paper describes a methodology that could be used by a utility to estimate the actual cost of congestion on its transmission system using limited, non-state estimator data. The assumed problem inputs are a power flow model of an entire interconnected grid (i.e., the eastern interconnect), costs for the utility's generators, and then hourly values of the utility's generation, load and tie-line flows over the study time period. Due to the common lack by most utilities of external measurements, the system is first equivalenced to retain only the utility's own internal buses and a small subset of the external buses. Then, for each hour, the utility's load and generation is set to match their historical values, while the external generation is adjusted to match the tie-line flows. Next, an economic dispatch is performed to determine the unconstrained cost. Finally, a security constrained OPF (SCOPF) is solved to take into account base case and contingent constraints. The methodology uses a complete ac power flow formulation to accurately estimate the impact of voltage constraints and the incremental impact of system losses. The inclusion of hydro generation is also considered. For illustrative purposes only, the methodology demonstrated on the TVA system using publicly available data transmission system data.
UR - http://www.scopus.com/inward/record.url?scp=84969583271&partnerID=8YFLogxK
UR - http://www.scopus.com/inward/citedby.url?scp=84969583271&partnerID=8YFLogxK
U2 - 10.1109/HICSS.2003.1173857
DO - 10.1109/HICSS.2003.1173857
M3 - Conference contribution
AN - SCOPUS:84969583271
T3 - Proceedings of the 36th Annual Hawaii International Conference on System Sciences, HICSS 2003
BT - Proceedings of the 36th Annual Hawaii International Conference on System Sciences, HICSS 2003
A2 - Sprague, Ralph H.
PB - Institute of Electrical and Electronics Engineers Inc.
T2 - 36th Annual Hawaii International Conference on System Sciences, HICSS 2003
Y2 - 6 January 2003 through 9 January 2003
ER -